The safety and reinstatement of the site is the responsibility of the applicant.
All road openings that involve excavation, trenching or boring on a Council road reserve must have a current Road Occupation Permit in place before any works are carried out. Reinstatement procedures are listed below and should be considered the minimum standard acceptable to Council. It is recommended that a Dial Before You Dig enquiry be made by phoning 1100 to ascertain the location of any underground services before works are carried out. Please note: The opening of any sealed road must be approved by the Asset Protection Officer.
Excavation Works
Excavations will be straight sided with no reverse slope to interfere with compaction of reinstatement material. The width of excavation should be wide enough to cater for mechanical compaction equipment. One metre clearance between the trench and existing trees is required unless authorised. Utility and service connections should be placed at a minimum of 600mm below ground level.
Reinstatement of an Unsealed Road Opening (Rock Surface)
The trench bed shall be thoroughly compacted before backfilling is carried out. Reinstatement material shall be 20mm, Class 3 F.C.R. and the trench will be reinstated in 150mm layers, mechanically compacted with moisture content at optimum. A crown of approximately 50mm is required to allow for future consolidation.
Reinstatement of a Sealed Road Ppening (Bituminous surface)
The trench bed shall be thoroughly compacted before backfilling is carried out. Reinstatement material shall be 20mm, Class3 F.C.R. and the trench will be reinstated in 150mm layers, mechanically compacted with moisture content at optimum. Reinstatement of all bituminous surfaces will be carried out by Bass Coast Shire Council only, at the permit holder’s expense.
Reinstatement of Nature Strip Opening (or similar surface)
The trench bed shall be thoroughly compacted before backfilling. Fill shall be compacted every 150mm as trench is reinstated. A minimum of 100mm of top soil shall be used in the final layer and an appropriate grass sown on the finished surface to complete the restoration. A crown of approximately 50 mm is required to allow for further consolidation.
General
The reinstatement must provide structural adequacy and serviceability that is at least equal to the condition of the site prior to the works. At completion, the works area shall be cleared of all surplus material and left in a neat and tidy condition. Please note: If the reinstatement is not completed to the above minimum standards the permit holder will be liable for any costs associated with bringing the area up to an acceptable standard.