Korumburra-Wonthaggi Road, Wonthaggi

Council has appointed SR Excavations Pty Ltd to carry out road pavement renewal works along the service road located adjacent to St Joseph Primary School on Korumburra-Wonthaggi Road, Wonthaggi.

These works will involve:

  • excavation of the existing pavement depth and replacing with new compacted rock
  • replacement of 100 metres of kerb and footpath to the front of the school
  • minor drainage works to assist with the protection of the new pavement; and
  • asphalt sealing works

These works started in January and will take 4-6 weeks to complete, subject to weather conditions.

This project is fully funded by Council in the order of $160,000.

Due to the nature of these works, there will be changes in traffic movements, including a full service land closure during the works. It is intended to carry out as much of the works as possible during the school holiday period to minimise disruption to school buses, parents and road users. However, it is expected there will be significant disruptions to traffic once school returns. Please obey all traffic control measures onsite and seek alternate parking/drop off areas, where appropriate.

We acknowledge it can be challenging to deliver the necessary works without affecting road users, businesses/school operations and general public access. Our contractor and staff will make every effort to minimise disruptions during construction.