Kerb and Pit Renewal Program - COMPLETED
You’ll find on this page:
Notice of Works
Bass Coast Shire Council has appointed SR Excavations Pty Ltd as part of our annual supply contract to undertake sections of kerb and pit renewal works as part of 2021-22 Capital Works program. These works are being rolled out on our road network in Cowes, Silverleaves, San Remo and Grantville.
Kerb and pit renewal works are needed to minimise the level of maintenance required in repairing road pavement’s due to loss of function in drainage infrastructure. The kerb and pit renewal works will ensure that stormwater flows freely to our underground drainage network. The projects listed below are also linked to our asphalt and spray sealing renewal programs (further information to be provided) which will start from November 2021 to February 2022.
The kerb and pit renewal program has begun and expected to be completed by end of October, weather permitting and any COVID restrictions. These works are fully funded by Council in the order of $165,000.
As part of these works, new concrete may be placed through landowner’s driveways. Access to their properties will be restricted for a four-day period following from when the concrete is poured. This is required to allow the concrete to set properly before any vehicles can use the driveway. Our contractor will advise residents, in advance, of any works affecting access to their properties.
Council acknowledges that it can be a challenge to deliver the necessary works and not affect road users, especially when much of the work is determined by weather conditions and availability of contractors. It is expected that there will be some delays to traffic during the works period. Contractors will take all necessary steps to minimise delays to road users. Our contractor will notify nearby residents and businesses that may be impacted by these works. Appropriate traffic control measures will be implemented onsite during these works.
We appreciate that these works may present an inconvenience to these landowners and we have asked for their patience during these times.
Location
The table below lists the streets to be improved by the kerb and pit renewal works.
Kerb and Pit Renewal program 2021/22 *
Road Name | Location |
Talofa Avenue - Chapel Street to Church Street | Cowes |
Perry Avenue - Rose Avenue to End Road | Cowes |
Broughton Avenue - Perry Avenue to Stradbroke Avenue | Cowes |
Roydon Road - Church Street to Robert Drive | Cowes |
Robert Drive - McKenzie Road to Court Bowl | Cowes |
Ellen Road - Coghlan Road to Woodland Avenue | Silverleaves |
Cleeland Street - Boys Home Road to School Avenue | Newhaven |
Bergin Grove - Marine Parade to Court Bowl | San Remo |
Thomas Grove - Bergin Grove to Ocean Grove | San Remo |
Agnes Street - Grantville Glen Alvie Road to Shepherd Road | Grantville |
Shepherd Road - Agnes Street to Court Bowl | Grantville |
Hopkins Drive - Shepherd Road to Robinson Crescent | Grantville |
Robinson Crescent - Hopkins Drive to Court Bowl | Grantville |
Staying Informed
For information or assistance during this project, please contact:
- SR Excavations Pty Ltd – Brad Hewton on 0429 598 819
- Bass Coast Shire Council’s Infrastructure Delivery Team – Marty O’Flynn or Infrastructure Asset Management Team – Simon Harris on 1300 BCOAST (226 278) or (03) 5671 2211
- Email basscoast@basscoast.vic.gov.au
- Visit our website www.basscoast.vic.gov.au for the latest updates on this project.